When
the Wisconsin Department of Transportation (WDOT) began
construction of State Highway 45 West near Clintonville, the
project appeared to be routine. Once underway, however, the
project took on an unusual course:
The
crew, having graded the road with base fill the night before,
would return to the job site each morning to find the grade
two feet low. This phenomenon continued for two straight weeks
until it was discovered that the weight of the fill was pushing
the underlying soils (thick black mud and peat moss) into the
adjacent, ten acre Brady Lake.
The
lake, prior to the start of Highway 45's construction,
averaged 18 feet in depth. Upon discovery of the shifting
soils, areas of the lake averaged less than nine inches of water cover.
The once pristine fishing lake, home to many
species of wildlife and dotted by a few residences, was
in danger of dying. As a result, the Wisconsin Department of
Natural Resources (WDNR), responsible for this state-owned
lake, intervened.
In
conjunction with the WDOT, the WDNR evaluated different
methods of restoring Brady Lake. Due to the physical size of
the property, the amount of material to be removed, and the
spoil handling issues involved, hydraulic dredging was
selected. Traditional heavy equipment (draglines or barge
mounted excavators) alternatives would have created either too
much potential for spillage and spoils handling problems, or it
would have been detrimental to the existing lake conditions by
resuspending much of the material to be removed. Draining the
lake and cleaning it out was not an acceptable option.
The
scope of work called for a floating dredge to excavate
material to a depth of 18 feet and pump it through an enclosed
pipeline 3,000 feet to a dry borrow pit. The difference in
elevation between the two areas was 110 feet. The WDNR
required that any water decanted from the spoils area to the
lake be returned at suspended solids levels no more than five
parts per million higher than pre-existing lake conditions.
The
WDNR/WDOT awarded the work at Brady Lake to J&S Dredging
of Arpin, Wisconsin. In July of 1991, J&S's owner, Mr. Jim
Mann, mobilized the Model 4010 Versi-Dredge™, manufactured
by Innovative Material Systems, Inc. (IMS) of Olathe, Kansas.
Unique for a one-truck transportable hydraulic dredge, it
operated standard to a depth of 20 feet.

Once
on site, the dredge was placed in the lake and the windlass
travel cable anchors set. The pipe was laid from the lake
through the highway's culvert and to the borrow pit. On shore,
a booster pump was added to maximize performance. Dredging
began shortly afterwards with the actual sediment removal
relatively routine. There were, however, two areas of added
attention: travel cable rigging and vegetation removal.
As
Brady Lake is kidney-shaped, one end having a width of nearly
1,000 feet and the other end having only a width of eight
feet, a standard, four point, bank-anchored cable travel
system was not possible. In its place, a three-anchor cable
travel system was used; two bank anchors in the rear,
connected by an adjustable cable and positioned with
tensioners to control lateral movement and a forward central
anchor with which to winch the dredge ahead. This
configuration provided a pie-shaped cut needed to perform the
job.
Nearer
the center of the lake, cattails had formed into several
floating "islands." These weeds, typically problems
for dredge pumps, were easily uprooted by removing the spoil
from underneath their roots. IMS' patented winglet
impeller, designed to pump trash and long, stringy objects,
then moved them through the pipeline and into the spoils area.
Cattails would, however, occasionally wrap around the
cutterbar and have to be cut off two to three times a day.
J&S
devised an ingenious system to return the water in spoils area
to Brady Lake at a suspended solids level that were no more
than five parts per million from existing lake amounts.
The
dry borrow pit was divided by a dike into two 300 foot wide by
1000 foot long cells. The slope of the dike ran from three
feet at the discharge end to eight feet at the overflow end.
At 200 foot intervals, a horizontal row of hay bales was put
down. The hay bales would progressively filter water as it
made its way toward the overflows. At the overflow, a silt
screen was put down to further filter any remaining water.
For
four hours a day water was pumped into one cell and then the
pipeline's flow was diverted, using a gate valve, to the
other cell for the remaining four hours. After leaving the
material to settle overnight, irrigation pumps were used to
pump the water to an adjacent 35 acre farm field. The land,
covered by vegetation and sloped toward the lake was lined on
the perimeters with hay bales that channeled any excess water
to the lake. The water entering the lake met all of the WDNR's
suspended solids criteria.
Since
the completion of the Brady Lake project, J&S has completed
numerous dredging projects in both the pristine water and the
industrial wastewater sectors. According to Jim Mann, "The
Versi-Dredge™ has been a great addition to our business.
We diversified our revenue stream and provided a profitable
service that was often requested by the customers of our sister
company J&S Liquid Systems - haulers of home, municipality and
dairy waste."
Source:
Land and Water
FOR
MORE INFORMATION, CONTACT:
Ryan Horton
IMS Marketing Director
Ph (913) 642-5100
Fax (913) 642-5119